• R999/1 DUBAI WATER CANAL PROJECT

Down
R999/1 DUBAI WATER CANAL PROJECT Haritada Gör
Year:2014-2016
Client:M/S. RTA
Contract Value:-
Consultant & Contractor:M/S. Parsons M/S. Mapa Günal Construction
Shoring & Excavation:
  • Secant Pile Shoring (880mm dia piles)
    • NDRC Driving pit
    • NDRC Receiving pit
    • Guide Wall and Capping beam construction
    • Strut and Waler Beam Construction
  • Kingpost Type Shoring Works around
  • the pile caps
  • Foundation Piling Works
    • 228 nos 1000mm & 1500mm dia with maximum 26m boring depth
  • Static Load Test for Working & NonWorking Piles (1000 and 1500 mm dia piles), Cross Hole Sonic Logging Test, Integrity Test, Caliper Logging Test