Year:2012
Client:Todini
Contract Value:-
Consultant & Contractor:Parsons
Shoring & Excavation: -   Installation And Extraction Of Sheet Piles At Unit 15& 16
-   Installation Of Temporary Sheet Piling Wall To Protect The Excavation Area On The Construction Of Units 15 & 16 At Underpass 
-   Extraction Of Sheet Piles
-   Total Used Numbers Of Sheet Piles Are 121 Numbers